Lien deadlines · United States
Wyoming lien deadlines (2026)
In Wyoming, the lien must be filed within 120 days from the last day you furnish, under Wyo. Stat. § 29-2-106(a).
The short answer
- File the lien: within 120 days from the last day you furnish (Wyo. Stat. § 29-2-106(a).
- Send the preliminary notice — Subcontractor / Supplier: within 30 days from the first day you furnish (Wyo. Stat. § 29-2-112.
- Start the enforcement action: within 180 days from the day the lien is recorded (Wyo. Stat. § 29-2-109.
Every Wyoming deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 30 days | from the first day you furnish | Right lost | Wyo. Stat. § 29-2-112 |
| Lien filing | All claimants | 120 days | from the last day you furnish | Right lost | Wyo. Stat. § 29-2-106(a) |
| Enforcement (suit) | All claimants | 180 days | from the day the lien is recorded | Right lost | Wyo. Stat. § 29-2-109 |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice §29-2-112: contractor — written notice of intent to lien before receiving any payment (incl. advance); sub/materialman — within 30 days after first furnishing, to the owner and the contractor. Failure bars the lien. A second notice (§29-2-107) is due >=20 days before filing.
- Lien filing §29-2-106(a): contractor — 150 days; every other claimant — 120 days, from the earlier of last work/materials or substantial completion (a recorded notice of substantial completion fixes the date). Shipped = 120-day branch. Filing extendable by written agreement.
- Enforcement (suit) §29-2-109: commence the action within 180 days after the lien statement is filed; the lien does not continue beyond 180 days unless suit is instituted.