In South Dakota, the lien must be filed within 120 days from the last day you furnish, under SDCL 44-9-15 (44-9-16/17).
The short answer
- File the lien: within 120 days from the last day you furnish (SDCL 44-9-15 (44-9-16/17).
- Send the preliminary notice — Sub-subcontractor / Supplier: within 60 days from the last day you furnish (SDCL 44-9-53 (with 44-9-50/51).
- Start the enforcement action: within 6 years from the last day you furnish (SDCL 44-9-24 (44-9-26 demand).
Every South Dakota deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Sub-subcontractor / Supplier | 60 days | from the last day you furnish | Context only | SDCL 44-9-53 (with 44-9-50/51) |
| Lien filing | All claimants | 120 days | from the last day you furnish | Right lost | SDCL 44-9-15 (44-9-16/17) |
| Enforcement (suit) | All claimants | 6 years | from the last day you furnish | Right lost | SDCL 44-9-24 (44-9-26 demand) |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice §44-9-53 (conditional): if the owner files a notice of project commencement (§§44-9-50/51), a sub-subcontractor or supplier must send a notice of furnishing by certified/registered mail within 60 days of last furnishing to keep lien-extension rights; laborers < $2,000 exempt.
- Lien filing §44-9-15: the lien ceases at the end of 120 days after the last work/materials unless the statement of claim is filed with the register of deeds; mailing a copy to the owner (receipt attached) is a condition precedent (§44-9-17).
- Enforcement (suit) §44-9-24: SIX YEARS after the last-item date stated in the filed lien statement (both '1 year' and '2 years' claims are wrong). TRAP §44-9-26: an owner/agent/contractor written demand to sue collapses it to 30 days.
Never miss a South Dakota deadline again