Lien deadlines · United States

Missouri lien deadlines (2026)

In Missouri, the lien must be filed within 6 months from the last day you furnish, under Mo. Rev. Stat. ch. 429.

3 rules Verified 2026-10-13Dataset confidence B Informational only — not legal advice How we verify

The short answer

Every Missouri deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier5 daysfrom the first day you furnishClaim limitedMo. Rev. Stat. ch. 429
Lien filingAll claimants6 monthsfrom the last day you furnishRight lostMo. Rev. Stat. ch. 429
Enforcement (suit)All claimants6 monthsfrom the day the lien is recordedRight lostMo. Rev. Stat. ch. 429

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice The consent rule is narrow: it applies only to owner-occupied residential property of four units or less. There, a subcontractor or supplier has no lien unless the owner signed a separate CONSENT OF OWNER clause in the written contract (Mo. Rev. Stat. § 429.013). Everywhere else the ordinary mechanics-lien rules apply.
  • Lien filing 6 months; Residential requires 10-day pre-lien notice