North Carolina lien deadlines (2026)

In North Carolina, the lien must be filed within 120 days from the last day you furnish, under N.C. Gen. Stat. § 44A-1 et seq.

3 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

Every North Carolina deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier15 daysfrom the first day you furnishRight lostN.C. Gen. Stat. § 44A-1 et seq.
Lien filingAll claimants120 daysfrom the last day you furnishRight lostN.C. Gen. Stat. § 44A-1 et seq.
Enforcement (suit)All claimants180 daysfrom the day the lien is recordedRight lostN.C. Gen. Stat. § 44A-1 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice For subcontractors on projects where the owner designates a lien agent (generally required on contracts of $40,000 or more), give the Notice to Lien Agent to the designated agent no later than 15 days after first furnishing labour or materials (N.C. Gen. Stat. § 44A-11.2).
  • Lien filing 120 days; Notice of claim of lien on funds required