Kentucky lien deadlines (2026)
In Kentucky, the lien must be filed within 6 months from the last day you furnish, under Ky. Rev. Stat. § 376.010 et seq.
The short answer
- File the lien: within 6 months from the last day you furnish (Ky. Rev. Stat. § 376.010 et seq..
- Send the preliminary notice — Subcontractor / Supplier: within 75 days from the last day you furnish (Ky. Rev. Stat. § 376.010 et seq..
- Start the enforcement action: within 1 year from the day the lien is recorded (Ky. Rev. Stat. § 376.010 et seq..
Every Kentucky deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 75 days | from the last day you furnish | Context only | Ky. Rev. Stat. § 376.010 et seq. |
| Lien filing | All claimants | 6 months | from the last day you furnish | Right lost | Ky. Rev. Stat. § 376.010 et seq. |
| Enforcement (suit) | All claimants | 1 year | from the day the lien is recorded | Right lost | Ky. Rev. Stat. § 376.010 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.