Lien deadlines · United States
Nebraska lien deadlines (2026)
In Nebraska, the lien must be filed within 120 days from the last day you furnish, under Neb. Rev. Stat. § 52-121 et seq.
The short answer
- File the lien: within 120 days from the last day you furnish (Neb. Rev. Stat. § 52-121 et seq..
- Preliminary notice — Subcontractor / Supplier: Must include verified itemized statement (Neb. Rev. Stat. § 52-121 et seq..
- Start the enforcement action: within 2 years from the day the lien is recorded (Neb. Rev. Stat. § 52-121 et seq..
Every Nebraska deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | no fixed window | from the first day you furnish | Context only | Neb. Rev. Stat. § 52-121 et seq. |
| Lien filing | All claimants | 120 days | from the last day you furnish | Right lost | Neb. Rev. Stat. § 52-121 et seq. |
| Enforcement (suit) | All claimants | 2 years | from the day the lien is recorded | Right lost | Neb. Rev. Stat. § 52-121 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Lien filing 120 days; Must include verified itemized statement
Never miss a Nebraska deadline again
Deadline 365 reads your job sheet every morning and tells you which notice or lien window is closing — for Nebraska and every other jurisdiction you work in. Every plan includes the 18-document lien pack.