Lien deadlines · United States

Montana lien deadlines (2026)

In Montana, the lien must be filed within 90 days from the last day you furnish, under Mont. Code § 71-3-521 et seq.

3 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

Every Montana deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier20 daysfrom the first day you furnishRight lostMont. Code § 71-3-521 et seq.
Lien filingAll claimants90 daysfrom the last day you furnishRight lostMont. Code § 71-3-521 et seq.
Enforcement (suit)All claimants2 yearsfrom the day the lien is recordedRight lostMont. Code § 71-3-521 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice Subcontractors must give the contracting owner a Notice of Right to Claim a Lien within 20 days after first furnishing, or within 45 days when a regulated lender finances a project that is not an owner-occupied residence. A late notice limits the lien to the work furnished in the 20 (or 45) days before notice was given (Mont. Code § 71-3-531). Send it by certified mail or deliver it personally.
  • Lien filing 90 days; Notice of right to claim lien required

Never miss a Montana deadline again