Lien deadlines · United States

Utah lien deadlines (2026)

In Utah, the lien must be filed within 180 days from project completion, under Utah Code § 38-1a-502.

4 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

  • File the lien: within 180 days from project completion (Utah Code § 38-1a-502.
  • Send the preliminary notice — Subcontractor / Supplier: within 20 days from the first day you furnish (Utah Code § 38-1a-501.
  • Start the enforcement action: within 180 days from the day the lien is recorded (Utah Code § 38-1a-701.
  • Watch the acceleration rule: within 90 days from project completion — a recorded notice can shorten every window above.

Every Utah deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier20 daysfrom the first day you furnishRight lostUtah Code § 38-1a-501
Lien filingAll claimants180 daysfrom project completionRight lostUtah Code § 38-1a-502
Enforcement (suit)All claimants180 daysfrom the day the lien is recordedRight lostUtah Code § 38-1a-701
Acceleration ruleAll claimants90 daysfrom project completionContext onlyUtah Code § 38-1a-507

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice §38-1a-501: file with the state registry within 20 days of commencing work — mandatory; late filing loses coverage for work before 5 days after filing, and it does nothing if filed more than 10 days after a notice of completion. Failure bars the lien (§501(e)).
  • Lien filing §38-1a-502: record the lien within 180 days after final completion of the original contract (no notice of completion), shortened to 90 days after a notice of completion is filed — never beyond 180 days. Subcontractors with work after CofO: 180 days from their own completion.
  • Enforcement (suit) §38-1a-701: file the enforcement action within 180 days after recording the lien (or preconstruction notice); record a notice of pendency in the same period or the lien is void against third parties; bankruptcy: 90 days after the stay lifts.
  • Acceleration rule Watch out: owner files a notice of completion (§38-1a-507) — record the lien within 90 days of that filing, and never later than 180 days after final completion of the original contract (§38-1a-502(1)(a)(ii)).