Quebec lien deadlines (2026)

In Quebec, the lien must be filed within 30 days from project completion, under Civil Code of Québec, art. 2727.

1 rule Verified 2026-10-19Dataset confidence B Informational only — not legal advice How we verify

The short answer

Every Quebec deadline

RuleWhoWindowClock startsIf missedStatute
Lien filingContractor / Subcontractor / Supplier30 daysfrom project completionRight lostCivil Code of Québec, art. 2727

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Lien filing A construction legal hypothec must be published within 30 days after the end of the work. Publication is the preservation step; enforce within the later period.