Lien deadlines · United States

Nevada lien deadlines (2026)

In Nevada, the lien must be filed within 90 days from the last day you furnish, under Nev. Rev. Stat. § 108.221 et seq.

3 rules Verified 2026-10-13Dataset confidence C Informational only — not legal advice How we verify

The short answer

Every Nevada deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier31 daysfrom the first day you furnishRight lostNev. Rev. Stat. § 108.221 et seq.
Lien filingAll claimants90 daysfrom the last day you furnishRight lostNev. Rev. Stat. § 108.221 et seq.
Enforcement (suit)All claimants6 monthsfrom the day the lien is recordedRight lostNev. Rev. Stat. § 108.221 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Lien filing 90 days; Notice of right to lien required for all

Never miss a Nevada deadline again