Maryland lien deadlines (2026)
In Maryland, the lien must be filed within 180 days from the last day you furnish, under Md. Code, Real Prop. § 9-101 et seq.
The short answer
- File the lien: within 180 days from the last day you furnish (Md. Code, Real Prop. § 9-101 et seq..
- Send the preliminary notice — Subcontractor / Supplier: within 120 days from the last day you furnish (Md. Code, Real Prop. § 9-101 et seq..
- Start the enforcement action: within 1 year from the day the lien is recorded (Md. Code, Real Prop. § 9-101 et seq..
Every Maryland deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 120 days | from the last day you furnish | Context only | Md. Code, Real Prop. § 9-101 et seq. |
| Lien filing | All claimants | 180 days | from the last day you furnish | Right lost | Md. Code, Real Prop. § 9-101 et seq. |
| Enforcement (suit) | All claimants | 1 year | from the day the lien is recorded | Right lost | Md. Code, Real Prop. § 9-101 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice Notice of intention to claim lien required for subcontractors
- Lien filing 180 days court petition; Notice of intention to claim lien required for subcontractors