District of Columbia lien deadlines (2026)
In District of Columbia, the lien must be filed within 90 days from the last day you furnish, under D.C. Code § 40-301.01 et seq.
The short answer
- File the lien: within 90 days from the last day you furnish (D.C. Code § 40-301.01 et seq..
- Preliminary notice: no fixed window listed for District of Columbia — the rule in the statute column is the one that applies.
- Start the enforcement action: within 180 days from the day the lien is recorded (D.C. Code § 40-301.01 et seq..
Every District of Columbia deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | no fixed window | from the first day you furnish | Context only | D.C. Code § 40-301.01 et seq. |
| Lien filing | All claimants | 90 days | from the last day you furnish | Right lost | D.C. Code § 40-301.01 et seq. |
| Enforcement (suit) | All claimants | 180 days | from the day the lien is recorded | Right lost | D.C. Code § 40-301.01 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.