Arkansas lien deadlines (2026)

In Arkansas, the lien must be filed within 120 days from the last day you furnish, under Ark. Code § 18-44-101 et seq.

3 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

Every Arkansas deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier75 daysfrom the last day you furnishClaim limitedArk. Code § 18-44-101 et seq.
Lien filingAll claimants120 daysfrom the last day you furnishRight lostArk. Code § 18-44-101 et seq.
Enforcement (suit)All claimants15 monthsfrom the day the lien is recordedRight lostArk. Code § 18-44-101 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice Arkansas uses a Notice to Owner form, but the rules depend on the project. On residential work the contractor gives the owner a Preliminary Notice before furnishing, and a subcontractor or materialman gives a written reservation of right before starting (Ark. Code § 18-44-115). On commercial work the claimant serves a Notice of Claim on the owner and the contractor within 75 days of last furnishing; every claimant also serves a Notice of Intent at least 10 days before filing (§ 18-44-114).
  • Lien filing 120 days; Residential requires 10-day pre-lien notice