Lien deadlines · United States

New York lien deadlines (2026)

In New York, the lien must be filed within 8 months from the last day you furnish, under N.Y. Lien Law art. 2.

4 rules Verified 2026-10-13Dataset confidence B Informational only — not legal advice How we verify

The short answer

  • File the lien: within 8 months from the last day you furnish (N.Y. Lien Law art. 2.
  • Preliminary notice — Subcontractor / Supplier: Residential: 4 months filing deadline (N.Y. Lien Law art. 2.
  • Start the enforcement action: within 1 year from the day the lien is recorded (N.Y. Lien Law art. 2.
  • Watch the acceleration rule: within 30 days from project completion — a recorded notice can shorten every window above.

Every New York deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplierno fixed windowfrom the first day you furnishContext onlyN.Y. Lien Law art. 2
Lien filingAll claimants8 monthsfrom the last day you furnishRight lostN.Y. Lien Law art. 2
Enforcement (suit)All claimants1 yearfrom the day the lien is recordedRight lostN.Y. Lien Law art. 2
Acceleration ruleAll claimants30 daysfrom project completionContext onlyN.Y. Lien Law 59

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Acceleration rule A Section 59 demand served by the owner gives you 30 days to start foreclosure, or the lien is vacated. The owner or lender may also not be served with your action.