Lien deadlines · United States

Tennessee lien deadlines (2026)

In Tennessee, the lien must be filed within 90 days from the last day you furnish, under Tenn. Code § 66-11-101 et seq.

4 rules Verified 2026-10-13Dataset confidence B Informational only — not legal advice How we verify

The short answer

Every Tennessee deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier90 daysfrom the first day you furnishRight lostTenn. Code § 66-11-101 et seq.
Monthly noticeCommercial subcontractors90 daysfrom the last day you furnishRight lostTenn. Code Ann. 66-11-145
Lien filingAll claimants90 daysfrom the last day you furnishRight lostTenn. Code § 66-11-101 et seq.
Enforcement (suit)All claimants1 yearfrom the day the lien is recordedRight lostTenn. Code § 66-11-101 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice There is no traditional pre-work notice, but a commercial subcontractor must send a monthly Notice of Nonpayment within 90 days after each month-end to preserve the lien for that month's work (Tenn. Code Ann. § 66-11-145).
  • Monthly notice monthly Notice of Nonpayment within 90 days of the last day of each month with unpaid work
  • Lien filing 90 days; Notice of nonpayment may be required