Lien deadlines · United States

Connecticut lien deadlines (2026)

In Connecticut, the lien must be filed within 90 days from the last day you furnish, under Conn. Gen. Stat. § 49-33 et seq.

3 rules Verified 2026-10-13Dataset confidence B Informational only — not legal advice How we verify

The short answer

Every Connecticut deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplierno fixed windowfrom the first day you furnishContext onlyConn. Gen. Stat. § 49-33 et seq.
Lien filingAll claimants90 daysfrom the last day you furnishRight lostConn. Gen. Stat. § 49-33 et seq.
Enforcement (suit)All claimants1 yearfrom the day the lien is recordedRight lostConn. Gen. Stat. § 49-33 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice Subcontractors must serve notice within 60 days
  • Lien filing 90 days; Subcontractors must serve notice within 60 days