Lien deadlines · United States

Alabama lien deadlines (2026)

In Alabama, the lien must be filed within 4 months from the last day you furnish, under Ala. Code § 35-11-215.

3 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

  • File the lien: within 4 months from the last day you furnish (Ala. Code § 35-11-215.
  • Preliminary notice — Subcontractor / Supplier: §35-11-218: anyone but the original contractor must give the owner written notice of the lien claim BEFORE filing the statement; after notice the owner's unpaid balance is held subject to the lien. Materialmen already noticed under §35-11-210 are exempt. (Ala. Code § 35-11-218 (see § 35-11-210).
  • Start the enforcement action: within 6 months from the last day you furnish (Ala. Code § 35-11-221.

Every Alabama deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplierno fixed windowfrom the first day you furnishClaim limitedAla. Code § 35-11-218 (see § 35-11-210)
Lien filingAll claimants4 monthsfrom the last day you furnishRight lostAla. Code § 35-11-215
Enforcement (suit)All claimants6 monthsfrom the last day you furnishRight lostAla. Code § 35-11-221

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice §35-11-218: anyone but the original contractor must give the owner written notice of the lien claim BEFORE filing the statement; after notice the owner's unpaid balance is held subject to the lien. Materialmen already noticed under §35-11-210 are exempt.
  • Lien filing §35-11-215: original contractor 6 months; every other person 4 months; journeyman/day laborer 30 days — after the last item of work/material. Shipped value = the 4-month branch (conservative).
  • Enforcement (suit) §35-11-221: action must commence within 6 months after maturity of the entire indebtedness (not the lien filing date). Tracked from last furnishing as the conservative floor — confirm the contract's maturity/payment terms.