Lien deadlines · United States
Alabama lien deadlines (2026)
In Alabama, the lien must be filed within 4 months from the last day you furnish, under Ala. Code § 35-11-215.
The short answer
- File the lien: within 4 months from the last day you furnish (Ala. Code § 35-11-215.
- Preliminary notice — Subcontractor / Supplier: §35-11-218: anyone but the original contractor must give the owner written notice of the lien claim BEFORE filing the statement; after notice the owner's unpaid balance is held subject to the lien. Materialmen already noticed under §35-11-210 are exempt. (Ala. Code § 35-11-218 (see § 35-11-210).
- Start the enforcement action: within 6 months from the last day you furnish (Ala. Code § 35-11-221.
Every Alabama deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | no fixed window | from the first day you furnish | Claim limited | Ala. Code § 35-11-218 (see § 35-11-210) |
| Lien filing | All claimants | 4 months | from the last day you furnish | Right lost | Ala. Code § 35-11-215 |
| Enforcement (suit) | All claimants | 6 months | from the last day you furnish | Right lost | Ala. Code § 35-11-221 |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice §35-11-218: anyone but the original contractor must give the owner written notice of the lien claim BEFORE filing the statement; after notice the owner's unpaid balance is held subject to the lien. Materialmen already noticed under §35-11-210 are exempt.
- Lien filing §35-11-215: original contractor 6 months; every other person 4 months; journeyman/day laborer 30 days — after the last item of work/material. Shipped value = the 4-month branch (conservative).
- Enforcement (suit) §35-11-221: action must commence within 6 months after maturity of the entire indebtedness (not the lien filing date). Tracked from last furnishing as the conservative floor — confirm the contract's maturity/payment terms.
Never miss an Alabama deadline again
Deadline 365 reads your job sheet every morning and tells you which notice or lien window is closing — for Alabama and every other jurisdiction you work in. Every plan includes the 18-document lien pack.