Lien deadlines · United States
Vermont lien deadlines (2026)
In Vermont, the lien must be filed within 180 days from the last day you furnish, under 9 V.S.A. § 1921 et seq.
The short answer
- File the lien: within 180 days from the last day you furnish (9 V.S.A. § 1921 et seq..
- Preliminary notice: no fixed window listed for Vermont — the rule in the statute column is the one that applies.
- Start the enforcement action: within 1 year from the day the lien is recorded (9 V.S.A. § 1921 et seq..
Every Vermont deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | no fixed window | from the first day you furnish | Context only | 9 V.S.A. § 1921 et seq. |
| Lien filing | All claimants | 180 days | from the last day you furnish | Right lost | 9 V.S.A. § 1921 et seq. |
| Enforcement (suit) | All claimants | 1 year | from the day the lien is recorded | Right lost | 9 V.S.A. § 1921 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.