In Vermont, the lien must be filed within 180 days from the last day you furnish, under 9 V.S.A. § 1921 et seq.

3 rules Verified 2026-10-13Dataset confidence B Informational only — not legal advice How we verify

The short answer

  • File the lien: within 180 days from the last day you furnish (9 V.S.A. § 1921 et seq..
  • Preliminary notice: no fixed window listed for Vermont — the rule in the statute column is the one that applies.
  • Start the enforcement action: within 1 year from the day the lien is recorded (9 V.S.A. § 1921 et seq..

Every Vermont deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplierno fixed windowfrom the first day you furnishContext only9 V.S.A. § 1921 et seq.
Lien filingAll claimants180 daysfrom the last day you furnishRight lost9 V.S.A. § 1921 et seq.
Enforcement (suit)All claimants1 yearfrom the day the lien is recordedRight lost9 V.S.A. § 1921 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Never miss a Vermont deadline again

Deadline 365 reads your job sheet every morning and tells you which notice or lien window is closing — for Vermont and every other jurisdiction you work in. Every plan includes the 18-document lien pack.

Lien deadlines in every jurisdiction