Oklahoma lien deadlines (2026)

In Oklahoma, the lien must be filed within 4 months from the last day you furnish, under Okla. Stat. tit. 42 § 141 et seq.

3 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

Every Oklahoma deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier75 daysfrom the last day you furnishRight lostOkla. Stat. tit. 42 § 141 et seq.
Lien filingAll claimants4 monthsfrom the last day you furnishRight lostOkla. Stat. tit. 42 § 141 et seq.
Enforcement (suit)All claimants1 yearfrom the day the lien is recordedRight lostOkla. Stat. tit. 42 § 141 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice Oklahoma subcontractors must send a pre-lien notice within 75 days after last furnishing if the claim
  • Lien filing 4 months; Pre-lien notice required for residential