Lien deadlines · United States
Ohio lien deadlines (2026)
In Ohio, the lien must be filed within 75 days from the last day you furnish, under Ohio Rev. Code § 1311.01 et seq.
The short answer
- File the lien: within 75 days from the last day you furnish (Ohio Rev. Code § 1311.01 et seq..
- Send the preliminary notice — Subcontractor / Supplier: within 21 days from the first day you furnish (Ohio Rev. Code § 1311.01 et seq..
- Start the enforcement action: within 6 years from the day the lien is recorded (Ohio Rev. Code § 1311.01 et seq..
Every Ohio deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 21 days | from the first day you furnish | Claim limited | Ohio Rev. Code § 1311.01 et seq. |
| Lien filing | GC | 75 days | from the last day you furnish | Right lost | Ohio Rev. Code § 1311.01 et seq. |
| Lien filing | Sub | 60 days | from the last day you furnish | Right lost | Ohio Rev. Code § 1311.01 et seq. |
| Enforcement (suit) | All claimants | 6 years | from the day the lien is recorded | Right lost | Ohio Rev. Code § 1311.01 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.