Lien deadlines · Canada
Manitoba lien deadlines (2026)
In Manitoba, the lien must be filed within 60 days from project completion, under Builders' Liens Act, C.C.S.M. c. B91, s. 43.
The short answer
- File the lien: within 60 days from project completion (Builders' Liens Act, C.C.S.M. c. B91, s. 43.
Every Manitoba deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Lien filing | Contractor / Subcontractor / Supplier | 60 days | from project completion | Right lost | Builders' Liens Act, C.C.S.M. c. B91, s. 43 |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Lien filing Register a claim for lien before or during the work, or within 60 days after substantial performance, abandonment, or the last work, services or materials, whichever applies.