Lien deadlines · Canada

Saskatchewan lien deadlines (2026)

In Saskatchewan, the lien must be filed within 40 days from project completion, under Builders' Lien Act, S.S. 1984-85-86, c. B-7.1, s. 49.

1 rule Verified 2026-10-19Dataset confidence B Informational only — not legal advice How we verify

The short answer

Every Saskatchewan deadline

RuleWhoWindowClock startsIf missedStatute
Lien filingContractor / Subcontractor / Supplier40 daysfrom project completionRight lostBuilders' Lien Act, S.S. 1984-85-86, c. B-7.1, s. 49

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Lien filing A lien expires 40 clear days after the triggering event (certificate, completion or abandonment, depending on the claimant). Confirm the trigger for the job.