Washington lien deadlines (2026)
In Washington, the lien must be filed within 90 days from the last day you furnish, under RCW ch. 60.04.
The short answer
- File the lien: within 90 days from the last day you furnish (RCW ch. 60.04.
- Send the preliminary notice — Subcontractor / Supplier: within 10 days from the first day you furnish (RCW ch. 60.04.
- Start the enforcement action: within 8 months from the last day you furnish (RCW ch. 60.04.
Every Washington deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 10 days | from the first day you furnish | Right lost | RCW ch. 60.04 |
| Lien filing | All claimants | 90 days | from the last day you furnish | Right lost | RCW ch. 60.04 |
| Enforcement (suit) | All claimants | 8 months | from the last day you furnish | Right lost | RCW ch. 60.04 |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Lien filing 90 days; Notice to owner/customer is strictly required
- Enforcement (suit) enforcement clock runs from LAST FURNISHING (not recording)