Lien deadlines · United States

Alaska lien deadlines (2026)

In Alaska, the lien must be filed within 120 days from the last day you furnish, under Alaska Stat. § 34.35.068.

4 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

  • File the lien: within 120 days from the last day you furnish (Alaska Stat. § 34.35.068.
  • Send the notice of right to lien (optional) — Subcontractor / Supplier: no deadline — give it before the first day you furnish (Alaska Stat. § 34.35.064.
  • Start the enforcement action: within 6 months from the day the lien is recorded (Alaska Stat. § 34.35.080(a).
  • Watch the acceleration rule: within 15 days from project completion — a recorded notice can shorten every window above.

Every Alaska deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / SupplierOptionalbefore you start furnishingContext onlyAlaska Stat. § 34.35.064
Lien filingAll claimants120 daysfrom the last day you furnishRight lostAlaska Stat. § 34.35.068
Enforcement (suit)All claimants6 monthsfrom the day the lien is recordedRight lostAlaska Stat. § 34.35.080(a)
Acceleration ruleAll claimants15 daysfrom project completionContext onlyAlaska Stat. § 34.35.068(b)

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice Optional notice of right to lien (§34.35.064) before furnishing — not required, but if the owner records a notice of completion, claimants who never sent it and had advance notice of the recording must record within 15 days (see Acceleration row).
  • Lien filing §34.35.068(a): record the claim of lien within 120 days after the claimant completes the contract or ceases to furnish labor/material/services/equipment — if no notice of completion is recorded. See the Acceleration row for the notice-of-completion trap.
  • Enforcement (suit) §34.35.080(a): a lien does not bind real property for more than 6 months after the claim of lien is recorded unless an action to enforce is commenced within that time (an extension notice recorded inside the 6 months restarts it).
  • Acceleration rule Watch out: owner records a notice of completion (§34.35.071) — claimants who received advance notice of the recording, or who never sent a notice of right to lien, must record the claim within 15 days after the recording (§34.35.068(b)(1)).