Lien deadlines · Canada
Alberta lien deadlines (2026)
In Alberta, the lien must be filed within 60 days from the last day you furnish, under Prompt Payment and Construction Lien Act, RSA 2000, c. P-26.4.
The short answer
- File the lien: within 60 days from the last day you furnish (Prompt Payment and Construction Lien Act, RSA 2000, c. P-26.4.
Every Alberta deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Lien filing | Contractor / Subcontractor / Supplier | 60 days | from the last day you furnish | Right lost | Prompt Payment and Construction Lien Act, RSA 2000, c. P-26.4 |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Lien filing Register a construction lien within 60 calendar days after the work is completed or the last materials are supplied. Oil and gas liens use a different 90-day period.