Lien deadlines · United States
California lien deadlines (2026)
In California, the lien must be filed within 90 days from the last day you furnish, under Cal. Civ. Code § 8000 et seq.
The short answer
- File the lien: within 90 days from the last day you furnish (Cal. Civ. Code § 8000 et seq..
- Send the preliminary notice — Subcontractor / Supplier: within 20 days from the first day you furnish (Cal. Civ. Code § 8000 et seq..
- Start the enforcement action: within 90 days from the day the lien is recorded (Cal. Civ. Code § 8000 et seq..
- Watch the acceleration rule: within 30 days from project completion — a recorded notice can shorten every window above.
Every California deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 20 days | from the first day you furnish | Right lost | Cal. Civ. Code § 8000 et seq. |
| Lien filing | All claimants | 90 days | from the last day you furnish | Right lost | Cal. Civ. Code § 8000 et seq. |
| Enforcement (suit) | All claimants | 90 days | from the day the lien is recorded | Right lost | Cal. Civ. Code § 8000 et seq. |
| Acceleration rule | All claimants | 30 days | from project completion | Context only | Cal. Civ. Code 8180-8190 |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice California's 20-Day Preliminary Notice is one of the most well-known preliminary notice requirement
- Lien filing 90 days (30 days with NOC); Strict preliminary notice requirement for all tiers
- Acceleration rule A recorded Notice of Completion or Notice of Cessation shortens a subcontractor's filing deadline from 90 days to 30 days. The owner or lender may also not be served with your action.