Lien deadlines · United States
Louisiana lien deadlines (2026)
In Louisiana, the lien must be filed within 60 days from the last day you furnish, under La. R.S. 9:4801 et seq.
The short answer
- File the lien: within 60 days from the last day you furnish (La. R.S. 9:4801 et seq..
- Preliminary notice — Subcontractor / Supplier: Notice of termination shortens deadlines (La. R.S. 9:4801 et seq..
- Start the enforcement action: within 1 year from the day the lien is recorded (La. R.S. 9:4801 et seq..
Every Louisiana deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | no fixed window | from the first day you furnish | Context only | La. R.S. 9:4801 et seq. |
| Lien filing | All claimants | 60 days | from the last day you furnish | Right lost | La. R.S. 9:4801 et seq. |
| Enforcement (suit) | All claimants | 1 year | from the day the lien is recorded | Right lost | La. R.S. 9:4801 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Lien filing 70 days from completion; Notice of termination shortens deadlines