Lien deadlines · Canada
Ontario lien deadlines (2026)
In Ontario, the lien must be filed within 45 days from the last day you furnish, under Construction Act, R.S.O. 1990, c. C.30, ss. 31, 34.
The short answer
- File the lien: within 45 days from the last day you furnish (Construction Act, R.S.O. 1990, c. C.30, ss. 31, 34.
Every Ontario deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Lien filing | Contractor / Subcontractor / Supplier | 45 days | from the last day you furnish | Right lost | Construction Act, R.S.O. 1990, c. C.30, ss. 31, 34 |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Lien filing Preserve a construction lien within 45 days after the last day of supply or completion, depending on the claimant and contract. Confirm the trigger that applies to the job.