Lien deadlines · United States
Virginia lien deadlines (2026)
In Virginia, the lien must be filed within 90 days from project completion, under Va. Code § 43-1 et seq.
The short answer
- File the lien: within 90 days from project completion (Va. Code § 43-1 et seq..
- Send the preliminary notice — Subcontractor / Supplier: within 30 days from the first day you furnish (Va. Code § 43-1 et seq..
- Start the enforcement action: within 6 months from the day the lien is recorded (Va. Code § 43-1 et seq..
Every Virginia deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 30 days | from the first day you furnish | Right lost | Va. Code § 43-1 et seq. |
| Lien filing | All claimants | 90 days | from project completion | Right lost | Va. Code § 43-1 et seq. |
| Enforcement (suit) | All claimants | 6 months | from the day the lien is recorded | Right lost | Va. Code § 43-1 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice Virginia has a very narrow notice requirement.
- Lien filing 90 days from month-end; Must include memorandum of lien
Never miss a Virginia deadline again
Deadline 365 reads your job sheet every morning and tells you which notice or lien window is closing — for Virginia and every other jurisdiction you work in. Every plan includes the 18-document lien pack.