Lien deadlines · United States

Virginia lien deadlines (2026)

In Virginia, the lien must be filed within 90 days from project completion, under Va. Code § 43-1 et seq.

3 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

Every Virginia deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier30 daysfrom the first day you furnishRight lostVa. Code § 43-1 et seq.
Lien filingAll claimants90 daysfrom project completionRight lostVa. Code § 43-1 et seq.
Enforcement (suit)All claimants6 monthsfrom the day the lien is recordedRight lostVa. Code § 43-1 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice Virginia has a very narrow notice requirement.
  • Lien filing 90 days from month-end; Must include memorandum of lien