Florida lien deadlines (2026)
In Florida, the lien must be filed within 90 days from the last day you furnish, under Fla. Stat. ch. 713.
The short answer
- File the lien: within 90 days from the last day you furnish (Fla. Stat. ch. 713.
- Send the preliminary notice — Subcontractor / Supplier: within 45 days from the first day you furnish (Fla. Stat. ch. 713.
- Start the enforcement action: within 1 year from the day the lien is recorded (Fla. Stat. ch. 713.
- Watch the acceleration rule: within 30 days from project completion — a recorded notice can shorten every window above.
Every Florida deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 45 days | from the first day you furnish | Right lost | Fla. Stat. ch. 713 |
| Lien filing | All claimants | 90 days | from the last day you furnish | Right lost | Fla. Stat. ch. 713 |
| Enforcement (suit) | All claimants | 1 year | from the day the lien is recorded | Right lost | Fla. Stat. ch. 713 |
| Acceleration rule | All claimants | 30 days | from project completion | Context only | Fla. Stat. 713.22 |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Lien filing 90 days; Notice to Owner is strictly required for subcontractors
- Acceleration rule A served Notice of Contest of Lien compresses the enforcement window from one year to 60 days. The owner or lender may also not be served with your action.