Lien deadlines · United States
Colorado lien deadlines (2026)
In Colorado, the lien must be filed within 4 months from the last day you furnish, under Colo. Rev. Stat. § 38-22-101 et seq.
The short answer
- File the lien: within 4 months from the last day you furnish (Colo. Rev. Stat. § 38-22-101 et seq..
- Preliminary notice — Subcontractor / Supplier: In Colorado, subcontractors are not required to send a preliminary notice, but they may choose to sen (Colo. Rev. Stat. § 38-22-101 et seq..
- Start the enforcement action: within 6 months from the last day you furnish (Colo. Rev. Stat. § 38-22-101 et seq..
Every Colorado deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | no fixed window | from the first day you furnish | Context only | Colo. Rev. Stat. § 38-22-101 et seq. |
| Lien filing | All claimants | 4 months | from the last day you furnish | Right lost | Colo. Rev. Stat. § 38-22-101 et seq. |
| Enforcement (suit) | All claimants | 6 months | from the last day you furnish | Right lost | Colo. Rev. Stat. § 38-22-101 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice In Colorado, subcontractors are not required to send a preliminary notice, but they may choose to sen
- Enforcement (suit) enforcement clock runs from LAST FURNISHING (not recording)