New Jersey lien deadlines (2026)
In New Jersey, the lien must be filed within 90 days from the last day you furnish, under N.J. Stat. § 2A:44A-1 et seq.
The short answer
- File the lien: within 90 days from the last day you furnish (N.J. Stat. § 2A:44A-1 et seq..
- Send the preliminary notice — Subcontractor / Supplier: within 60 days from the last day you furnish (N.J. Stat. § 2A:44A-1 et seq..
- Start the enforcement action: within 1 year from the day the lien is recorded (N.J. Stat. § 2A:44A-1 et seq..
Every New Jersey deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 60 days | from the last day you furnish | Claim limited | N.J. Stat. § 2A:44A-1 et seq. |
| Lien filing | All claimants | 90 days | from the last day you furnish | Right lost | N.J. Stat. § 2A:44A-1 et seq. |
| Enforcement (suit) | All claimants | 1 year | from the day the lien is recorded | Right lost | N.J. Stat. § 2A:44A-1 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice In New Jersey, preliminary notices are only required on residential projects.
- Lien filing 90 days commercial; NOC filing can shorten deadlines