Lien deadlines · United States

West Virginia lien deadlines (2026)

In West Virginia, the lien must be filed within 100 days from the last day you furnish, under W. Va. Code §§ 38-2-8, 38-2-11, 38-2-13.

3 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

Every West Virginia deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplierno fixed windowfrom the first day you furnishContext onlyW. Va. Code art. 38-2
Lien filingAll claimants100 daysfrom the last day you furnishRight lostW. Va. Code §§ 38-2-8, 38-2-11, 38-2-13
Enforcement (suit)All claimants6 monthsfrom the day the lien is recordedRight lostW. Va. Code § 38-2-34

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice No pre-work preliminary notice in W. Va. Code art. 38-2. The 'notice of lien' (§§38-2-8/11/13) is a POST-work perfection step — served on the owner and recorded within 100 days (see Filing row).
  • Lien filing §38-2-8: GC records the notice of lien within 100 days after completing its contract work; §38-2-13: sub/laborer must serve the owner AND record within 100 days; §38-2-11: materialman same. Recording alone is not enough for subs.
  • Enforcement (suit) §38-2-34(a): an action to enforce must commence in circuit court within 6 months after the notice of lien is filed, or the lien is discharged; one lienholder's timely action preserves the others. Single-family owner-occupied: liability limited (§34(b)).

Never miss a West Virginia deadline again

Deadline 365 reads your job sheet every morning and tells you which notice or lien window is closing — for West Virginia and every other jurisdiction you work in. Every plan includes the 18-document lien pack.