Lien deadlines · United States
South Carolina lien deadlines (2026)
In South Carolina, the lien must be filed within 90 days from the last day you furnish, under S.C. Code § 29-5-10 et seq.
The short answer
- File the lien: within 90 days from the last day you furnish (S.C. Code § 29-5-10 et seq..
- Send the notice of furnishing — Subcontractor / Supplier: no fixed deadline — send it as soon as work begins (S.C. Code § 29-5-10 et seq..
- Start the enforcement action: within 6 months from the day the lien is recorded (S.C. Code § 29-5-10 et seq..
Every South Carolina deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | No fixed window | send it as soon as work begins | Claim limited | S.C. Code § 29-5-10 et seq. |
| Lien filing | All claimants | 90 days | from the last day you furnish | Right lost | S.C. Code § 29-5-10 et seq. |
| Enforcement (suit) | All claimants | 6 months | from the day the lien is recorded | Right lost | S.C. Code § 29-5-10 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Preliminary notice A subcontractor not in direct contract with the owner gives a written notice of furnishing; the statute sets no deadline, so send it as soon as work begins. A sub-subcontractor or supplier must send it to the contractor by certified or registered mail to escape the aggregate lien cap (S.C. Code § 29-5-20(B)).
Never miss a South Carolina deadline again
Deadline 365 reads your job sheet every morning and tells you which notice or lien window is closing — for South Carolina and every other jurisdiction you work in. Every plan includes the 18-document lien pack.