Lien deadlines · United States

South Carolina lien deadlines (2026)

In South Carolina, the lien must be filed within 90 days from the last day you furnish, under S.C. Code § 29-5-10 et seq.

3 rules Verified 2026-10-13Dataset confidence C Informational only — not legal advice How we verify

The short answer

Every South Carolina deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / SupplierNo fixed windowsend it as soon as work beginsClaim limitedS.C. Code § 29-5-10 et seq.
Lien filingAll claimants90 daysfrom the last day you furnishRight lostS.C. Code § 29-5-10 et seq.
Enforcement (suit)All claimants6 monthsfrom the day the lien is recordedRight lostS.C. Code § 29-5-10 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Preliminary notice A subcontractor not in direct contract with the owner gives a written notice of furnishing; the statute sets no deadline, so send it as soon as work begins. A sub-subcontractor or supplier must send it to the contractor by certified or registered mail to escape the aggregate lien cap (S.C. Code § 29-5-20(B)).