Lien deadlines · United States

Oregon lien deadlines (2026)

In Oregon, the lien must be filed within 75 days from the last day you furnish, under Or. Rev. Stat. § 87.005 et seq.

3 rules Verified 2026-10-13Dataset confidence A Informational only — not legal advice How we verify

The short answer

Every Oregon deadline

RuleWhoWindowClock startsIf missedStatute
Preliminary noticeSubcontractor / Supplier8 daysfrom the first day you furnishRight lostOr. Rev. Stat. § 87.005 et seq.
Lien filingAll claimants75 daysfrom the last day you furnishRight lostOr. Rev. Stat. § 87.005 et seq.
Enforcement (suit)All claimants120 daysfrom the day the lien is recordedRight lostOr. Rev. Stat. § 87.005 et seq.

Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.

Statute notes

Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.

  • Lien filing 75 days; Notice of right to lien required for all