Lien deadlines · United States
Oregon lien deadlines (2026)
In Oregon, the lien must be filed within 75 days from the last day you furnish, under Or. Rev. Stat. § 87.005 et seq.
The short answer
- File the lien: within 75 days from the last day you furnish (Or. Rev. Stat. § 87.005 et seq..
- Send the preliminary notice — Subcontractor / Supplier: within 8 days from the first day you furnish (Or. Rev. Stat. § 87.005 et seq..
- Start the enforcement action: within 120 days from the day the lien is recorded (Or. Rev. Stat. § 87.005 et seq..
Every Oregon deadline
| Rule | Who | Window | Clock starts | If missed | Statute |
|---|---|---|---|---|---|
| Preliminary notice | Subcontractor / Supplier | 8 days | from the first day you furnish | Right lost | Or. Rev. Stat. § 87.005 et seq. |
| Lien filing | All claimants | 75 days | from the last day you furnish | Right lost | Or. Rev. Stat. § 87.005 et seq. |
| Enforcement (suit) | All claimants | 120 days | from the day the lien is recorded | Right lost | Or. Rev. Stat. § 87.005 et seq. |
Window = the statutory limit. Clock starts = the event the window runs from. Statute links open the code text on a public legal source.
Statute notes
Verbatim notes from the verified dataset, with dataset shorthand removed. Read the statute before you rely on them.
- Lien filing 75 days; Notice of right to lien required for all
Never miss an Oregon deadline again